Multilateral Funding Works

Completed and Ongoing

Independent Engineer / Construction Supervision / Authority Engineer

Sr. No.

Name of the Project

Client

Length (In Km)

Status

1.

Consultancy Services for Supervision of Civil Works for Madhya Pradesh District Road II Sector Project (MPDRIISP) Package-1 (Bhopal) Funded by: Asian Development Bank.

M.P.      Road Development Corporation Ltd.,   Bhopal (M.P.)

296.87;

intermediate Lane

Completed

2.

Consultancy Services for Supervision  0f Civil Works for Madhya Pradesh District Connectivity Sector Project (MPDCSP) Package

-2 (Jabalpur); Length : 375.59 Km; Funded by: Asian Development Bank.

M.P.      Road Development Corporation Ltd.,   Bhopal (M.P.)

375.59;

intermediate Lane

Completed

3.

Consultancy Services for Preparation of Feasibility Study and Detailed Project Report for various State Highways & MDR under Package – 1 (Indore) in the State of Madhya Pradesh; Funded By : New Development Bank

MP PWD

808.94;

2 Lane

Completed

4.

Consultancy Services for Preparation of Feasibility Study and Detailed Project Report for Package – 2(Bhopal) in the State of Madhya Pradesh funded by New Development Bank (NDB).

MP PWD

615.36;

2 Lane

Completed

5.

Consultancy Services For Feasibility Study And Detailed Project Report For Improvement to Phaltan Shingnapur Mhaswad Shenwadi District Border to Nimbode Road MDR 13 Section Phaltan Shingnapur Mhaswad Shenwadi Satara District Border Km 2/290 to Km 86/250 Dist. Satara Under Maharashtra Road Improvement Project (MRIP) with Financial Assistance From Asian Development Bank (ADB) Package No. DPR – 8 (Length: 83.96 Km)

Public Works Division, Maharashtra

83.96 Km; 2 Lane

Work On Progress

6.

Consultancy Services For Feasibility Study And Detailed Project Report For Improvement to Kolhapur  Ring  Road  from  N.H.4  Jajal  Petrol

Public Works Division, Maharashtra

99.10 Km; 2 Lane

Work On Progress

 

Pump to Kaneri Girgaon S.H.196 Nandwal Washi Mahe Koge Kuditre Factory S.H.177 Wakare Fhata Khupire Yavluj Varange Kerli Nigave Top Nagaon Mouje Vadgaon Herle S.H. 204 Rukadi Fhata Rukadi Chinchwad Vasagade Sangwade Halswade Vikaswadi to N.H.4 Jajal Petrol Pump Road S.H. 194 A Km 30/00 to Km 36/00 & Km 75/00 to Km 80/00 Dist. Kolhapur; Improvement to Kolhapur Chikhali Varanage Padali Bajarbhogaon Padsali Anuskura Road Km 9/900 to  Km 32/00 & Km 32/00 to Km 51/500 Dist. Kolhapur; Improvement to MSH 6 to Atigre Kabnoor Ichalkarnji Takwade Shirdhon Kurundwad Akiwat Takali Khidrapur Road Km 16/00 to Km 26/00 & Km 36/00 to Km 44/00 Dist. Kolhapur; Improvement to NH 204 to Kerli Kotoli Nandgaon Nanadari Road SH 191 Road Km 0/00 to Km 29/500 Dist. Kolhapur Under Maharashtra Road  Improvement Project (MRIP) with Financial Assistance From Asian Development Bank (ADB) Package No. DPR – 11 (Length: 99.10 Km)

 

 

 

7.

Consultancy Services For Feasibility Study And Detailed Project Report For  Improvement to road Brahmni Chandrapur Yavatmal Badnera Amravati Paratwada Harisal Dharni Tq. Amravati,                              Achalpur & Bhatkuli Km 182/00 to Km 223/800 Dist. Yavatmal; Improvement to road Brahmni Chandrapur Yavatmal Badnera Amravati Paratwada Harisal Dharni Tq.Nandgaon Khandeshwar Km 223/800 to 260/600 Dist. Amravati Under Maharashtra Road Improvement Project (MRIP) with Financial Assistance From Asian Development Bank (ADB)

Package No. DPR – 15 (Length: 78.60 Km)

Public Works Division, Maharashtra

78.60 Km; 2 Lane

Work On Progress

8.

Consultancy Services For Feasibility Study And Detailed Project Report For Improvement to Road Brahmni Chandrapur Yavatmal Badnera Amravati Paratwada Harisal Dharni Tq. Amravati,

 

Achalpur & Bhatkuli Km 260/600 to                       Km 312/600   Distt.   Amravati;   Improvement   to Badnera  Anjangaon  Bari  Malkhed  Chandhur Railway Dhamangaon Railway SH – 296, Km 0/00  to  Km  26/500  Distt.  Amravati  Under Maharashtra                       Road    Improvement                       Project (MRIP) with Financial Assistance From Asian Development Bank (ADB) Package No. DPR – 16 (Length: 78.50 Km)

Public Works Division, Maharashtra

78.50 Km; 2 Lane

Work On Progress

9.

Consultancy services For Feasibility Study And Detailed Project Report For Improvement to State Border to Salwade Bhrahmanwel Devala Lasalgaon  Vinchur  Savalivihir  Bharwas  Chas

Public Works Division, Maharashtra

94.50 Km; 2 Lane

Work On Progress

 

Road (SH-7) km.215/00 to 244/00 Tal- Kopargaon Dist-Ahmednagar.  (Section- Aurangabad-Nashik Road to Sinner- Shirdi Road) Dist. Ahmednagar; Improvement to Bari to Ghoti Sinnar Highway Km 191/980 to Km 205/380 Dist. Nashik; Improvement to Saptashrungi Gad Nanduri Abona Kanashi Manur Aliyabad road  SH-21 Tal.  Kalwan Km 0/00 to Km 52/00 Dist. Nashik Under Maharashtra Road Improvement Project (MRIP) with  Financial  Assistance  From Asian Development Bank (ADB) Package No. DPR – 20 (Length: 94.50 Km)

 

 

 

10.

Consultancy Services For Feasibility Study And Detailed Project Report For Improvement to Hingoli Aunda Hatta Purana Palam Ranisawargaon Road SH-249 Km 127/00 to 163/00 Tq Palam and SH-235 to Banvas Tadudwadi Matadwadi SH-249 Ranisawargaon Dampuri SH-248 Pipaldari Antarveli SH-234 MDR-19 KM 20/00 TO 34/500 Tq. Gangakhed Dist. Parbhani;

 

Improvement to SH-248 to Malsonna Dathna Deulgaon Dudhate Dhanora Kale Nila SH-61 to Mirkhel Join to SH-235 MDR-15 KM 0/00 TO 25/00 Tq. Purna Dist.     Parbhani                                                     Under Maharashtra Road Improvement Project (MRIP) with  Financial  Assistance  From Asian Development Bank (ADB) Package No. DPR – 24 (Length: 75.50 Km)

Public Works Division, Maharashtra

75.50 Km; 2 Lane

Work On Progress

11.

Consultancy Services For Feasibility Study And Detailed Project Report For Improvement to Ahmadpur Ghotka Shindagi Kurula Kandhar Barul Gadaga Road SH-56 Km 218/00 to 248/500. Tq. Kandhar Dist. Nanded; Improvement to Malegaon Balegaon Karegaon phata Babli phata bellur to Naigaon to shate border MDR – 83 Km 46/400 to 93/700 Dist. Nanded           Under Maharashtra Road Improvement Project (MRIP) with Financial Assistance From Asian Development Bank (ADB) Package No. DPR – 27 (Length: 77.30 Km)

Public Works Division, Maharashtra

77.30 Km; 2 Lane

Work On Progress

12.

Consultancy Services For Feasibility Study And Detailed Project Report For Improvement to M.S.H.- 5 to Undangaon Halda Khamkheda Shedurni to District      Border Road Km 81/00 to Km 123/500 & Km 0/00 to 26/00 Dist. Aurangabad; Improvement to Bharadi Ghatnandra Tidka SH- 40 Km 70/00 to Km 103/00 Dist. Aurangabad Under Maharashtra Road Improvement Project (MRIP) with Financial Assistance From Asian Development

Public Works Division, Maharashtra

101.50 Km; 2 Lane

Work On Progress

 

Bank  (ADB)  Package  No.  DPR  –  28  (Length:

101.50 Km)